Template:Short description Template:Distinguish Loss of load in an electrical grid is a term used to describe the situation when the available generation capacity is less than the system load.Template:Sfn Multiple probabilistic reliability indices for the generation systems are using loss of load in their definitions, with the more popularTemplate:Sfn being Loss of Load Probability (LOLP) that characterizes a probability of a loss of load occurring within a year.Template:Sfn Loss of load events are calculated before the mitigating actions (purchasing electricity from other systems, load shedding) are taken, so a loss of load does not necessarily cause a blackout.
Loss-of-load-based reliability indices
Multiple reliability indices for the electrical generation are based on the loss of load being observed/calculated over a long interval (one or multiple years) in relatively small increments (an hour or a day). The total number of increments inside the long interval is designated as (e.g., for a yearlong interval if the increment is a day, if the increment is an hour):Template:Sfn
- Loss of load probability (LOLP) is a probability of an occurrence of an increment with a loss of load condition. LOLP can also be considered as a probability of involuntary load shedding;Template:Sfn
- Loss of load expectation (LOLE) is the total duration of increments when the loss of load is expected to occur, . Frequently LOLE is specified in days, if the increment is an hour, not a day, a term loss of load hours (LOLH) is sometimes used.Template:Sfn Since LOLE uses the daily peak value for the whole day, LOLH (that uses different peak values for each hour) cannot be obtained by simply multiplying LOLE by 24;Template:Sfn although in practice the relationship is close to linear, the coefficients vary from network to network;Template:Sfn
- Loss of load events (LOLEV) a.k.a. loss of load frequency (LOLF) is the number of loss of load events within the interval (an event can occupy several contiguous increments);Template:Sfn
- Loss of load duration (LOLD) characterizes the average duration of a loss of load event:Template:Sfn
One-day-in-ten-years criterion
A typically accepted design goal for is 0.1 day per yearTemplate:Sfn ("one-day-in-ten-years criterion"Template:Sfn a.k.a. "1 in 10"Template:Sfn), corresponding to . In the US, the threshold is set by the regional entities, like Northeast Power Coordinating Council:Template:Sfn Template:Quote